Horizon Middle School - Round 3 Bid Packages (GC/CM Sub-Bids - LK Clark Group)

NOTE: Each “Bid Pack” will have a specific time. The bid time shown below is for the next scheduled bid package and will be updated as the schedule proceeds. For a complete list of "Bid Packs" and their times, please see below. The current North Pines Middle School occupies 2 acres of a 10-acre site just north of Spokane, Washington, and is approximately 85,000 sq. ft. in size and is a grade 6-7-8 school. The new facility will be approximately 90,000 sq. ft., and will house up to 600 students grades 6, 7 and 8. There will be limited field and activities area work with the exception of the civil and parking areas.

Status

Bidding Closed

Prebid Date5/14/19 4:00 pm

Bid Date5/23/19 4:00 pm

Company & Contacts

Leone and Keeble, Inc.

Brendan Monroe, bmonroe@leone-keeble.com 327-4451   Chad Schmidt, CSchmidt@nacarchitecture.com

Location

Spokane Valley, WA

Bidders may download electronic files at no cost. Printed documents are available, at Bidders expense, by choosing the “Order” option.

A pre-bid conference is scheduled for Tuesday May 14, 2019 at 4:00 PDT. Those interested in attending should meet in the Community Room at Chester Elementary School located at 3525 S Pines Rd, Spokane Valley, WA 99206. This conference is not mandatory for prospective bidders; however, we strongly encourage all interested bidders to attend.

The following bid packages must be submitted to the district office on or before 3:00 p.m. PDT.
BP04 – Masonry
BP13 – Building Insulation and Vapor Barrier
BP16 – Sanitary Wall Coverings (FRP)
BP28 – Specialties
BP31 – Gymnasium equipment
BP32 – Site furnishings
This is a General Contractor/Construction Manager (GC/CM) project. LK Clark Group is the GC/CM on the project and intends to bid on packages 16, 28, 31, & 32.

The following bid packages must be submitted to the district office on or before 4:00 p.m. PDT.
BP9 – Chain link fences and gates
BP20 – Overhead Doors & Sectional Doors
BP23 – Floor coverings
BP24 – Wood athletic flooring
BP25 – Acoustical ceilings & acoustical wall panels
BP26 – Painting & water repellents
BP27 – Wall coverings
BP33 – Window coverings