City of Spirit Lake Well No. 5 Construction, 2019 - ARI

The project includes drilling and installation of proposed Well No. 5, construction of a pump house, installation of a well head building, completion of an overflow pond, site access and parking improvements, site fencing construction, completion of underground distribution piping, piping interconnections into the existing City system, installation of chlorination equipment, and all associated appurtenances to make a complete and operable system.

Status

Bidding Closed

Prebid Date4/16/19 9:20 am

Bid Date5/2/19 2:00 pm

Company & Contacts

James A. Sewell and Associates

Kevin Koesel, kkoesel@jasewell.com   (509) 447-3626

Location

Spirit Lake, ID

At the Owners request, Bidders may obtain the project and bid information from their plan room at ‘www.jasewellplans.com

Plan Centers may download the project information from ‘www.abadandistribution.com’