Fairfield 2020 Patching & Crack Sealing

Schedule A Base Bid work consists of completing approximately 600 square yards of pavement patching, including sawcutting, removal of existing pavement, and placing new crushed surfacing and HMA and crack sealing along Carlton Road from First St (SR-27) to 3rd and along Main Street, McNeil Street, Ticknor Street, and Fairweather Street surrounding the Town’s Upper Park. Schedule B Additive Alternate work consists of approximately 400 square yards of additional pavement patching that will be completed as funding allows.

Status

Accepting Bids

Bid Date5/29/20 11:00 am

Company & Contacts

Century West Engineering

Bryan Hicks bhicks@centurywest.com   (509) 838-3810

Location

Fairfield, WA

Project Estimate: $75,000.00 to $90,000.00